移动模架制梁专项施组施工方案目录
第一章 编制依据及原则··········································································· - 1 -
一、编制目的....................................................... - 1 -
二、编制依据....................................................... - 1 -
三、编制原则....................................................... - 2 -
四、适用范围....................................................... - 2 -
第二章 工程概况······················································································ - 2 -
一、工程简介....................................................... - 2 -
二、自然条件....................................................... - 3 -
四、工程特点及重点.................................................. - 4 -
第三章 施工的总体规划··········································································· - 4 -
一、总体施工方案.................................................... - 4 -
二、施工队伍安排及劳动力计划........................................ - 5 -
三、施工组织机构.................................................... - 5 -
四、设备组织....................................................... - 6 -
第四章 进度安排和工期保证措施······························································ - 6 -
一、工期安排....................................................... - 6 -
二、工期保证措施.................................................... - 6 -
三、工期控制方法.................................................... - 7 -
第五章 施工准备······················································································ - 8 -
一、技术准备....................................................... - 8 -
二、现场准备....................................................... - 8 -
三、人员培训....................................................... - 9 -
第六章 DSZ32m/900t上行自行式移动模架················································ - 9 -
一、DXZ32/900t上行式移动模架系统介绍................................ - 9 -
二、施工周期...................................................... - 20 -
三、移动模架现场拼装与试验......................................... - 20 -
四 移动模架主要工作原理、施工工艺流程和步骤.......................... - 22 -
第七章 箱梁施工工艺及方法··································································· - 23 -
一、支座安装...................................................... - 25 -
二、预拱度设置..................................................... - 27 -
三、钢筋及预埋铁件施工............................................. - 28 -
四、混凝土施工..................................................... - 31 -
五、预应力施工..................................................... - 35 -
六、施工质量通病预防及措施......................................... - 40 -
第八章 劳动力组织计划········································································ - 43 -
一、劳动力配置计划................................................. - 43 -
二、劳动力进场计划................................................. - 43 -
第九章 材料、设备供应计划及保证措施·················································· - 43 -
一、材料、设备供应计划............................................. - 43 -
二、材料供应保证措施............................................... - 43 -
三、主要材料使用控制................................................ - 44 -
第十章 质量保证措施············································································· - 44 -
一、质量管理机构................................................... - 44 -
二、质量保证体系框图............................................... - 45 -
三、工序质量控制责任制............................................. - 47 -
四、各工序质量控制................................................. - 48 -
第十一章 安全保证措施·········································································· - 52 -
一、移动模架施工安全管理机构....................................... - 52 -
二、建立健全各项安全制度........................................... - 52 -
三、安全教育与培训................................................. - 53 -
四、注重技术安全,抓好方案论证...................................... - 54 -
五、高空作业安全保证措施........................................... - 54 -
六、移动模架施工安全措施........................................... - 54 -
七、预应力施工安全措施............................................. - 55 -
八、施工用电安全保证措施........................................... - 55 -
九、防雷措施...................................................... - 56 -
第十二章 文明施工及环境保护措施························································· - 56 -
一、文明施工管理机构............................................... - 56 -
二、文明施工措施................................................... - 56 -
三、环境保护措施................................................... - 57 -
第十三章 冬、夏季施工措施··································································· - 58 -
一、冬季施工措施................................................... - 58 -
二、夏季施工措施................................................... - 60 -
第十四章 应急预案················································································· - 60 -
一、应急机制...................................................... - 60 -
二、应急工作原则................................................... - 62 -
三、应急工作程序................................................... - 63 -
四、应急预防措施................................................... - 63 -